Spaces:
Sleeping
Sleeping
AMGEN Lockout/Tagout Procedure | |
Plant: AOH Case Packer and Palletizer | |
ester Machine Unit 1 Line2 | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4. isolate | |
all energy sources by switching E1 to “OFF” position. iolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6 Disipate any residual energy 7. Very | |
complete de-energuzation of all sources by pressing start button on the machine, | |
‘Main electrical | |
panel on the side | |
‘of the machine. | |
‘Main electrical | |
panel on the side | |
of the machine. | |
Main air-line next | |
tomachine | |
Main air-line next | |
tomachine | |
Turn off breaker | |
handle | |
Turn off breaker | |
handle bd | |
Tumoffairvalve | AL | |
Tumoffairvalve | AZ | |
1. Only the person who nstaled the lockouttagout device's alowed to remove | |
2. Ensue il tools and equipment have been removed 3. Confirm all employees are accounted for 4 | |
‘Vert that al controls aren a neutal state 5, Remove lockouttagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations. | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
IMA Labeler | |
IMA Machine Unit 1 Line | |
Lockout/Tagout Application Process. | |
1. Prepare for shutdown 2. Notify al affected personnel 3. Properly shut down the machine 4. Isolate | |
all energy sources by switching E1 to “OFF” position. isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6. Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine. | |
Plant: AQH | |
Source Magnitude L lethod Symbol | |
‘480v Main electrical | |
BoEn a! panelontheside | Twmoftbreaker | gy | |
‘of the machine mn | |
S0Psi Mainair ine next | Tum offairvalve | Al | |
tomachine | |
Lockout/Tagout Removal Process | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Cartoner | |
Dividella Machine Unit 1 Line | |
Lockout/Tagout Application Process | |
1L. Prepare for shutdown 2. Notify al affected personnel 3. Properly shut down the machine 4. Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6, Disipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine. | |
Plant: AQH | |
eee nequires | |
(ra Tene own | |
Magnituc | |
480v | |
Symbol | |
Energy Sourc: | |
Main electrical | |
‘Turn off breaker | |
Electrical panel on the | |
‘of the machine handle | |
‘94psi Main air-line next | 7.15 off air valve Al | |
tomachine | |
LockoutTagout Removal Process | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
Weiler Machine Unit 2 Line 1 | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4. isolate | |
all energy sources by switching El to “OFF” positon. isolate compressed ai by closing Al valve to off | |
position. S. Apply lockout devices to all identified locations 6. Disipate any residual energy 7. Verify | |
complete de-energiation of al sources by pressing start button on the machine. | |
Plant: AOH | |
ree Magnitude | |
230v Main electrical | |
Electrical panel on the side | |
of the machine | |
90psi Main air-line next | |
tomachine | |
Lockout/Tagout Removal Process | |
Only the person who installed the lckouvtagout device Is alowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confiem all employees are accounted for 4, | |
‘Very that all controls are in a neutral state . Remove lockouv/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Symbol | |
Turn off breaker | |
handle el | |
Tum offairvalve | AL | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Contact Accumulator | |
FARGO Machine Unit 1 Line | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Notify al affected personnel 3. Properly shut down the machine 4. Isolate | |
all energy sources by switching E1 to “OFF” position. isolate compressed air by closing Al valve to off | |
position. S. Apply lockout devices to all identified locations 6, Dissipate any residual energy 7. Verify | |
complete de-energization ofall sources by pressing start button on the machine. | |
Plant: AQH | |
stor | |
Magnitude symbol | |
480v Main electrical | |
Cad panelontheside | Twmoftbreaker | gy | |
‘of the machine randle | |
90psi__| Main air-line next | |
to machine Turn offairvalve | AL | |
Lockout/Tagout Removal Process | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Case Packer and Palletizer | |
ester Machine Unit 1 | |
Plant: AOH | |
e1 | |
1. Prepare for shutdown 2. Not all affected personnel 3. Properly shut down the machine 4 slate | |
ail energy sources by switching Eto “OFF” postion. lolate compressed ai by closing Al valve to off | |
‘position. 5. Apply lockout devices to all dented locations 6. Disipate any residual energy 7. Very | |
compete de-energzation of al sources by pressing start button on the machine. | |
‘Main electrical | |
panel on the side | |
‘of the machine. | |
‘Main electrical | |
panel on the side | |
of the machine. | |
Main air-line next | |
tomachine | |
Main air-line next | |
tomachine | |
Turn off breaker | |
handle | |
Turn off breaker | |
handle bd | |
Tumoffairvalve | AL | |
Tur off air valve | |
1. Only the person who nstaled the lockouttagout device's alowed to remove | |
2. Ensue il tools and equipment have been removed 3. Confirm all employees are accounted for 4 | |
‘Vert that al controls aren a neutal state 5, Remove lockouttagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations. | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Machine | |
Line2 | |
Plant: AQH | |
1. Prepare for shutdown 2. Notify all affected personnel 8. Properly shut down the machine 4. Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing At valve to off | |
position. 5. Apply lockout devices to all identified locations 6. Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine, | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
‘Weiler Machine Unit 1 Line | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Not ll affected personnel 3. Properly shut down the machin 4. solat | |
all energy sources by switching Eto “OFF” position. lolate compressed air by closing Al valve to off | |
position. S. Apply lockout devices to al identifi locations 6, Disipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine. | |
Plant: AH | |
Method | |
Main electrical | |
‘Tum off breaker | |
Electrical panel on the side el | |
of the machine handle | |
‘90psi Main airline next | Turn ottairvave | AL | |
tomachine | |
Lockout/Tagout Removal Process | |
"Only the person who installed the lockouttagout device is alowed 10 remove | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4 | |
‘erty that all controls are in a neural state 5, Remove lockoutNagout devices | |
6. Reenergize machine 7. Test equipment for corect operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
Weiler Machine Unit 3 Line | |
Lockout/Tagout Application Process | |
‘L Prepare for shutdown 2. Not all affected personnel 3. Properly shut down the machine . Isolate | |
all energy sources by switching E1 to “OFF” position. solate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6. Dislpate any residual energy 7. Verify | |
complete de-energization of al sources by pressing start button on the machine. | |
Plant: AOH | |
ree Magnitude | |
230v Main electrical | |
Electrical panel on the side | |
of the machine | |
90psi Main air-line next | |
tomachine | |
Lockout/Tagout Removal Process | |
Only the person who installed the lckouvtagout device Is alowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confiem all employees are accounted for 4, | |
‘Very that all controls are in a neutral state . Remove lockouv/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Symbol | |
Turn off breaker | |
handle el | |
Tum offairvalve | AL | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Plant: AOH Autoinjector Machine | |
ATS Machine Unit 3 Line1 | |
|. Prepare for shutdown 2. Notify all affected personnel 8. Properly shut down the machine 4, Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6, Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine, | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
‘Weiler Machine Unit Line | |
Lockout/Tagout Application Process | |
1L Prepare for shutdown 2. Nott all affected personnel 3. Properly shut dow the machine 4, isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to al identified locations 6. Disipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing stat button on the machine. | |
Plant: AH. | |
Method | |
Main electrical | |
Electrical panelontheside | Twnottbreaker | py | |
of the machine wane | |
S0psi__ | Mainair-inenext | +. oftairvave | AL | |
tomachine | |
Lockout/Tagout Removal Process | |
"Only the person who installed the lockouttagout device is alowed 10 remove | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4 | |
‘erty that all controls are in a neural state 5, Remove lockoutNagout devices | |
6. Reenergize machine 7. Test equipment for corect operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Plant: AOH Autoinjector Machine | |
ATS Machine Unit 4 2 | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut dovin the machine 4. Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6. Dissipate any residual energy 7. Verity | |
complete de-energization of all sources by pressing start button on the machine | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
Lockout/Tagout Procedure | |
Autoinjector Machine | |
‘ATS Machine Unit Lined | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4, Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6, Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine. | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Plant: AOH Autoinjector Machine | |
ATS Machine Unit 2 el | |
1. Prepare for shutdown 2. Notify al affected personnel 3. Properly shut down the machine 4 Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to all identified locations 6. Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine. | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
IMA Labeler | |
IMA Machine Unit 1 ine 2 | |
Plant: AOH | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4 Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
postion. . Apply lockout devices to all identified locations 6. Disipate any residual energy 7. Verify | |
‘complete de-energization ofall sources by pressing start button on the machine. | |
Main electrical | |
panel on the side | |
of the machine | |
Main air-line next | |
tomachine | |
Turn off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
‘Weiler Machine Unit Line | |
Lockout/Tagout Application Process | |
1L Prepare for shutdown 2. Nott all affected personnel 3. Properly shut dow the machine 4, isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. 5. Apply lockout devices to al identified locations 6. Disipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing stat button on the machine. | |
Plant: AH. | |
Method | |
Main electrical | |
Electrical panelontheside | Twnottbreaker | py | |
of the machine wane | |
S0psi__ | Mainair-inenext | +. oftairvave | AL | |
tomachine | |
Lockout/Tagout Removal Process | |
"Only the person who installed the lockouttagout device is alowed 10 remove | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4 | |
‘erty that all controls are in a neural state 5, Remove lockoutNagout devices | |
6. Reenergize machine 7. Test equipment for corect operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Plant: AOH Autoinjector Machine | |
ATS Machine Unit 4 ine1 | |
1. Prepare for shutdown 2, Notify al affected personnel 3. Properly shut down the machine 4. Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by losing Al valve to off | |
position. §. Apply lockout devices to al identified locations 6. Dissipate any residual energy 7. Verity | |
complete de-energization ofall sources by pressing start button on the machine. | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Cartoner | |
(ella Machine Unit 1 Line2 | |
Plant: AQH | |
Di | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4. isolate | |
all energy sources by switching £1 to “OFF” position. olate compressed alr by closing Al valve to off | |
postion. 5. Apply lockout devices tall dented location 6. islpate any resial energy 7. Verify | |
complete de-energiztion of all sources by pressing start button on the machine. | |
eee nequires | |
(ra Tene own | |
Magnituc | |
480v | |
Symbol | |
Energy Sourc: | |
Main electrical | |
‘Turn off breaker | |
Electrical panel on the | |
‘of the machine handle | |
‘94psi Main air-line next | 7.15 off air valve Al | | |
tomachine | |
LockoutTagout Removal Process | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
Weiler Machine Unit 2 Line2 | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Notify al afected personnel 3. Properly shut down the machine 4 Isolate | |
all energy sources by swrtchingE1 to “OFF” postion. lolate compressed air by closing Al valve to off | |
postion. 5. Apply lockout devices to all identified locations 6. Disipate any residual energy 7. Verify | |
complete de-energization of al sources by pressing start button onthe machine | |
Plant: AOH | |
Symbol | |
230v | |
Electrical panctontheside | ToffBreaker | py | |
of the machine jandle | |
S0psi | Mainair-line next - | |
naire next | Turn offairvalve | AL | |
Lockout/Tagout Removal Process | |
Only the person who installed the lckouvtagout device Is alowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confiem all employees are accounted for 4, | |
‘Very that all controls are in a neutral state . Remove lockouv/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Labeler | |
Weiler Machine Unit 3 Line 2 | |
Plant: AOH | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Nttyallaffeted personne! 3. Properly shut down the machine 4. isolate | |
all energy sources by switching €1 to “OFF” postion. rolate compressed air by closing Al valve to off | |
Postion. 5. Apply lockout devices to al identified locations 6, Dissipate any residual energy 7. Verify | |
complete de-enerization ofall sources by pressing start button onthe machine. | |
Symbol | |
230v | |
Electrical panctontheside | ToffBreaker | py | |
of the machine jandle | |
S0psi | Mainair-line next - | |
naire next | Turn offairvalve | AL | |
Lockout/Tagout Removal Process | |
Only the person who installed the lckouvtagout device Is alowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confiem all employees are accounted for 4, | |
‘Very that all controls are in a neutral state . Remove lockouv/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Autoinjector Machine | |
‘ATS Machine Unit 3 Line 2 | |
Plant: AOH | |
1. Prepare for shutdown 2. Nott all affected personnel 3. Properly shut down the machine 4, Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed air by closing Al valve to off | |
position. . Apply lockout devices to all identified locations 6. Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine | |
Magnitu Method | |
480v Main electrical | |
panel on the side of | |
the machine | |
7O0psi_—_| Main air-line next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Plant: AOH Autoinjector Machine | |
ATS Machine Unit 1 Line 2 | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4. Isolate | |
all energy sources by switching E1 to "OFF” position. Isolate compressed air by closing A1 valve to off | |
position. 5. Apply lockout devices to all identified locations 6, Dissipate any residual energy 7. Verify | |
complete de-energization of all sources by pressing start button on the machine. | |
Main electrical | |
panel on the side of | |
the machine | |
Main airline next to | |
machine | |
Tum off breaker | |
handle | |
Turn off air valve | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |
AMGEN Lockout/Tagout Procedure | |
Contact Accumulator | |
FARGO Machine Unit 1 Line 2 | |
Lockout/Tagout Application Process | |
1. Prepare for shutdown 2. Notify all affected personnel 3. Properly shut down the machine 4, Isolate | |
all energy sources by switching E1 to “OFF” position. Isolate compressed alr by closing Al valve to off | |
Position. 5. Apply lockout devices to all identified locations 6. Dissipate any residual energy 7. Verity | |
complete de-energization of all sources by pressing start button on the machine. | |
Plant: AOH | |
Magnitude symbol | |
480v Main electrical | |
Gosie | panel on the side Turn off breaker iat | |
of the machine indie | |
90psi Main air-line next | |
to machine Turn offairvalve | AL | |
Lockout/Tagout Removal Process | |
1. Only the person who installed the lockouttagout device is allowed to remove it | |
2. Ensure all tools and equipment have been removed 3. Confirm all employees are accounted for 4, | |
Verify that all controls are in a neutral state §. Remove lockout/tagout devices | |
6. Reenergize machine 7. Test equipment for correct operation and resume normal operations | |
Internal Use Only Health Safety and Environment | |
Alternative Protection Measures | |
‘Some servicing operations performed during normal production operations are excepted from coverage | |
under the Lockout/Tagout standard. This exception is referred to asthe minor servicing exception. | |
Minor Servicing Exceptions must meet the following criteria: | |
1. The activity must be conducted during normal production operations. | |
2. The activity must be routine, repetitive, and integral | |
‘a Routine - The activity must be a regular course of procedure and be in accordance with | |
established practices. | |
b. Repetitive - The activity must be regularly repeated as part of the production process. | |
Integral: The activity must be essential to the production process. | |
3. There must be alternative protection measures to provide effective protection from | |
hazardous energy. | |
Procedure Explanations: | |
This procedure applies to all Amgen personnel as well as any outside contractors that are either Primary | |
‘Authorize Person (PAP), Authorized and Reviewer to perform Lockout/Tagout or affected by this | |
Lockout/Tagout procedure. | |
A Lockout/Tagout is required for maintenance and servicing activities such as: | |
Constructing, installing, adjusting, inspecting, modifying, and maintaining and/or servicing machines or | |
equipment | |
Repairing and/or maintaining equipment during normal production operations require a Lockout/Tagout | |
if | |
‘An employee is required to remove or bypass a guard or other safety device | |
‘An employee is required to place any part of his or her body into an area on a machine or piece of | |
equipment where work is performed (point of operation) or where an associated danger zone exists | |
during a machine operating cycle The purpose of this procedure is to prevent equipment from accidently | |
being energized by an unknowing employee. As a result of this procedure an energy isolating device | |
must be installed on each of the labeled disconnect locations. | |
Internal Use Only Health Safety and Environment | |
Only employees that have been formally trained and authorized to perform Lockout/Tagout procedures | |
should be servicing a machine. All affected employees shall be notified anytime there is work to be done | |
intheir area. | |
There are detailed steps under the “Lockout/Tagout Application Process” section that identify each step | |
in the lockout process in numerical order. All steps should be followed in numerical order without | |
skipping any step. | |
Each picture will show the energy isolating location on the machine. Labeling methods include either E | |
(Electrical), M (Mechanical), W (Water), A (Air) and followed by a red arrow pointing to the energy | |
isolating device or measure. The identified energy source will allow employees servicing or performing, | |
maintenance operations to know the steps and visually see where locks should be applied. | |
‘A key is provided to define the energy source type, the location of the isolating mechanism, the method | |
to effectively use the isolating mechanism, and the symbol that will identify the visual location, | |
Under the “Lockout/Tagout Removal Process” the key steps of removing a lock or tag are listed in | |
numerical order. Each step should be completed in its entirety before moving to the next. | |
Testing or Positioning | |
Lockout/Tagout still must be used when troubleshooting or testing equipment. When Lockout/Tagout | |
devices must temporarily be removed, the following steps must be followed: | |
1. Clear machine of tools, equipment, etc. | |
2. Ensure all employees are clear of the danger zone | |
3. Remove Lockout/Tagout devices | |
4. Energize and proceed with testing (Must wear any required PPE including but not limited to | |
‘Arc Flash wear, safety goggles, specialized gloves, etc.) | |
De-energize all systems and reapply energy control measures, | |
Internal Use Only Health Safety and Environment | |